Dry building technology of CCEWOOL light weight insulation bricks

     Last week we introduced wet building technology of CCEWOOL light weight insulating brick, this week we are going to introduce dry building technology of CCEWOOL light weight insulation bricks.
1. General rules
(1) The material and specification of CCEWOOL light weight insulation brick and packing must meet the design requirements.
(2) The appearance of CCEWOOL light weight insulation brick should be in good condition. And can not be used if the brick is seriously damaged.
(3) The filling material for brick seam should be dry and good in performance. If there is damp or grouting, it should be sieved before being used.
(4) Dry building of light weight insulation brick should be built in staggered masonry.
2. Inspection before dry building
(1) Before building, the kiln shell and related accessories should be installed and checked.
(2) When the construction of refractory fire brick or refractory castables is finished first. The construction quality of brick masonry and pouring body should meet the normal construction requirement of the insulating masonry, and the height should be suitable.
(3) When need to build in narrow groove between the shell and the masonry. The bricks, mud and other debris in the narrow slot must be removed thoroughly.
Above is the dry building method of CCEWOOL lightweight insulation brick. Hope this can bring help to furnace builders and contractors. Next week we will continue to introduce dry building method of CCEWOOL lightweight insulation brick.